MIL-DTL-24215D
4. VERIFICATION
4.1 Test equipment and inspection facilities. Test and measuring equipment and inspection facilities of
sufficient accuracy, quality and quantity to permit performance of the required inspection shall be
established and maintained by the supplier. The establishment and maintenance of a calibration system
to control the accuracy of the measuring and test equipment shall be in accordance with NCSL-Z540.3.
4.2 Classification of inspections. The inspections specified herein are classified as follows:
a. Materials inspection (see 4.3).
b. First article inspection (see 4.5).
c. Conformance inspection (see 4.6).
4.3 Materials inspection. Materials inspection shall consist of certification supported by verifying data
that the materials listed in table I, used in fabricating the attenuator, are in accordance with the applicable
referenced specifications or requirements prior to such fabrication.
TABLE I. Materials inspection.
Material
Requirement
Applicable specification
paragraph
Fungus
Silver
Copper-beryllium
Steel bars, shapes and forgings
4.4 Inspection conditions. Unless otherwise specified herein, all inspections shall be performed in
accordance with the test conditions specified in the "GENERAL REQUIREMENTS" of MIL-STD-202.
4.5 First article inspection. First article inspection shall be performed by the supplier after award of
contract and prior to production, at a location acceptable to the Government. First article inspection shall
be performed on sample units that have been produced with equipment and procedures normally used in
production. First article approval is valid only on the contract or purchase order under which it is granted,
unless extended by the Government to other contracts or purchase orders. First article inspection shall
consist of the tests specified in table II, in the order shown.
4.5.1 Sample. One attenuator from each 50, or fraction thereof produced, shall be subjected to first
article inspection as specified in table II.
4.5.2 Failures. Failures in any of the examinations or tests shall be cause for refusal to grant first
article approval of the attenuators represented by the sample unit.
6